working Plans

To coordinate the research activities and prepare working plans, Working Plan & Research Circle was formulated under a Chief Conservator of Forests with overall supervision from Additional Principal Chief Conservator of Forests (Planning). Under the supervision of the Chief Conservator of Forests Working plans are prepared by the Working Plan Officers. They are assisted by Range Officers.

Working Plans

Working Plan Code 2004 

Sl. No. Forest Division
Currency of Present Working Plan
GOI Approval
No. & Date
WPO
Present Status
1
 Achenkovil03/2018
No.F (C) A/11.6/250/WP KER Dated 31-12-2007
  
 2 Chalakkudy03/2015
No. F (C) A/11.6/101/MISC/KER dated 07-02-2006
  
 3 Kannur* 03/2011 No. F (C) A/11.6/63/KER dated 09-01-2002

Asif. P.K. 9847021801

0497 -2760394

 Part I- Feb
 4 Konni*03/2011
No. F (C) A/11.6/44/MISC  dated 28-12-2001 Jayakrishnan
 Part I-March
 5 Kothamangalam 03/2011 
No. F (C) A/11.6/61/WP/KER  dated 07-11-2001 K.C. Prasad
 Part I- Feb 3 yrs extension proposal submitted on 02.11.2010
 6  Kottayam03/2015
No. F (C) A/11.6/82/MISC  dated 07-07-2006  
 7 Kozhikode 03/2021 No. F(C)
A/11.6/73/MISC/434 dated 10-01-2012
  
 8 Malayattoor 03/2012 No. F(C)
A/11.6/75/MISC/2400
dated 11-03-2003
 Radhakrishnan, ACF, NSC, Kalady 
9
 Mankulam 03/2011
 No. F(C)
A/11.6/98//MISC/KER1649
dated 18-11-2002
 K.C. Prasad
 Draft Presented on 16.12.2011. Corrections are to be attended
 10 Mannarkkad2022-23
No. F(C)
A/11.6/25/KER dated 09-08-2012
 Sasi Kumar.C 
 11 Marayoor03/2020
 No. F (C) A/11.6/283/KER dated 16/03/2011  
 12 Munnar 03/2020
 No. F (C)A/11.6/72/KER dated 16-03-2011  
 13  Nenmara03/2011
 No. F(C)
A/11.6/64/WP/KER/20308  dated 06-02-2004
 Saju Varghese, ACF, Research Unit, Olavakkode 

Part - I March

Part - II Aug
 14 

Nilambur (N)*

03/2011
 No. F(C)
A/11.6/79/MISC/KER/511
dated 17-06-2002

 T.K.Sivarajan,ACF,Nilambur(N) Division

9847021261

9447979063

04931-220232

 

Part - I Feb

Part - II May
 15 Nilambur (S)*03/2011
 No. F(C)
A/11.6/78/MISC
dated 19-04-2001

 K.A. Mohd. Zainulabdeen, ACF,SIP,o/o CCF(EC),PKD

9847021532

0491-2555389

 

Part - I Feb

Part - II May
 16 Palakkad03/2019
 No. F(C)
A/11.6/35/93/MISC
dated 24-09-2009
  
 17 Punalur
 03/2021 No. F(C)
A/11.6/77/MISC/388 dated 03-01-2012
  
 18  Ranni03/2012
 No. F(C)
A/11.6/62/WP/KER
dated 25-03-2003
 S. SUN 

Draft Working Plan will be sent to Bangalore during 2nd Week of Dec 2014

 19  Thenmala 03/2019 No. F(C)
A/11.6/35/93
dated 24-09-2009
  
 20 Thiruvananthapuram03/2014
 No. F(C)
A/11.6/60/WP dated 06-04-2005
  
 21 Thrissur03/2010
 No. F(C)
A/11.6/74/MISC dated 08-06-2000
  Sabu K.R. Pending with CCF (WP&R)
 22 Vazhachal 03/2012 No. F(C)
A/11.6/36/94/KER/1618
dated 11-11-2003
 Sheik Hyder Hussain TA, o/o CCF (CC) TCR 

Part - I Feb

Part - II Oct
 23 

 Wayanad (N)*

 03/2011 No. F(C)
A/11.6/81/MISC/410
dated 27-05-2003
 Madhusoodanan, TA,o/o CCF, Kannur Part - I May
 24 Wayanad (S) 03/2011 No. F(C)
A/11.6/100/KER
dated 13-08-2001
 Sajikumar,ACF, SF Extn. KKD (i/c of WPO KKD) 

Part - I May

Part - II

* Management Plan Period

Last Updated (Thursday, 18 December 2014 15:42)